As of 28 Oct 2026
Builder · Bengaluru · Category B
Sterling Developers
Also filed as Sterling Developers Private Limited: merged here so one promoter reads as one record.
- Projects tracked
- 3
- 2 hand-researched
- RERA registrations
- 5
- 0 completed
- Overdue share
- 60%
- past latest filed completion
- Average slip
- 37 mo
- promised vs post-extension
Sterling Developers has 3 residential projects in the DOSL corpus, concentrated in Bellandur, Hebbal, Whitefield. 2 carry hand-researched pricing and diligence notes; the rest are traced from Karnataka RERA registrations.
Across every registration Sterling Developers has filed with Karnataka RERA (5 in total, merged across the promoter's SPVs and alias spellings), 0 are recorded complete and 3 are past their latest filed completion date, an overdue share of 60%, with an average schedule slip of 37 months.
The promoter has been registering projects since 2015-09-15, most recently in 2023-05-02, covering 25 units in total.
Disputes & cases
Court cases on Sterling Developers and its land, and buyer complaints on its other projects, are in each project's full report, under Disputes & cases. Open a report from the project list below.
Where Sterling Developers builds
All 3 Sterling Developers projects
Median builder quote across those with a published price: ₹12,963/sqft.
| Sterling AscentiaNearing completion | Bellandur | Apartment | 1,591–2,015 sqft | ₹13,100–14,850/sqft | 2026 | 63 B |
| Sterling Villa GrandeReady to move | Whitefield | Villa | 3,000–4,675 sqft | ₹11,500–12,400/sqft | Mar 2024 | 51 C |
| Sterling PointeUnder construction | Hebbal | Apartment | – | ₹12,150–14,850/sqftindicative | Nov 2023 | 62 B* |
Sterling Developers: common questions
- Does Sterling Developers deliver on time?
- Across 5 Karnataka RERA registrations, 3 are past their latest filed completion date, an overdue share of 60%, with an average slip of 37 months between the completion date first promised and the one after extensions. For context, the median overdue share among Bengaluru's curated Category-A builders is around 38% and the weighted-median slip is roughly 21 months, so schedule slip is the market norm rather than the exception.
- How many projects does Sterling Developers have in Bengaluru?
- 3 are tracked here, across 3 localities including Bellandur, Hebbal, Whitefield. Each has its own page, and its own full report with the filed schedule, unit mix, land schedule and unsold-inventory trend.
Track-record figures are computed from Sterling Developers’s own Karnataka RERA filings, merged across the promoter’s SPVs and alias spellings.