Overview
Overview
Overview

| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | 1 | 2 | Review |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| 38 & BanyanCompleted · OC 30-03-2022 | ASSETZ BUILDWELL LLP | Apartment | 1,833 sqft carpet (as filed) | Completed |
| Ambaram HomesCompleted (regulator flag) | ARR DEVELOPERS | Apartment | 879 sqft carpet (as filed) | Completed |
| Amber MeadowsCompleted · OC 31-05-2024 | Excel Stone Developers | Apartment | – | Completed |
| Anuraag AmoghLapsed · completion date passed | ANURAAG CONSTRUCTIONS | Apartment | 736–949 sqft carpet (as filed) | Dec 2024 |
| Ashish A N Reddy ApartmentLapsed · completion date passed | AASHISH DEVELOPER AND BUILDERS | Apartment | 817 sqft carpet (as filed) | Sep 2023 |
| Atz ArevaLapsed · completion date passed | ATZ PROPERTIES | Apartment | 804–1,042 sqft carpet (as filed) | Jun 2026 |
Title & ownership
Approvals
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
What we read
Source: K-RERA project page and the documents filed there, as read by us. 20 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Valuation |
|---|
| – |
| – |
| – |
| Not verified |
| Location & risks | – | 2 | 1 | Review |
|---|
| Construction & progress | – | – | 1 | Clear |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| AuraActive · 9% built | BLUE SKY PROPERTIES | Apartment | 1,089 sqft carpet (as filed) | Apr 2030 |
| Blue Meadows Phase 2Active · 75% built | Yuva Infinity Developers | Apartment | 757–956 sqft carpet (as filed) | Dec 2027 |
8 of 61 other projects in Balagere, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Desire Tree in the interactive atlas
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
| Building plan (BDA) | Not verified yet | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire department | Filed with the registration | |
| Environmental clearance | SEIAA 75 CON 2019 · issued 23 Aug 2019 | Clear |
| AAI | Filed with the registration | |
| Pollution board (CFE) | Filed with the registration | |
| Water and sewerage NOC (BWSSB) | issued 24 Jun 2021 | |
| RERA extensions | Granted · Approved 20 Jan 2026 | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 20 Jan 2027 |
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
2BHK 44.4%3BHK 34.7%Block-B 3BHK 8%A-Block-2BHK 5.3%4 other types 7.6%
| 2BHK | 100 units · 786 sq ft carpet | |
|---|---|---|
| 3BHK | 78 units · 944 sq ft carpet | |
| A-Block-2BHK | 12 units · 821 sq ft carpet | |
| Block-B 2BHK | 4 units · 705 sq ft carpet | |
| Block-B 3BHK | 18 units · 994 sq ft carpet | |
| Block a-3BHK | 11 units · 1,143 sq ft carpet | |
| Ground Floor-B-Block-2BHKK | 1 units | |
| Ground Floor-B-Block-3BHK | 1 units · 1,023 sq ft carpet |
| Sold, Q3 2025-26 | 95 / 225 | |
|---|---|---|
| Unsold, Q3 2025-26 | 130 |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Residential (main), at the filed pin | Clear |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | 930 m, Varthur police station | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | 100 m to the south, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 190 m to the north-west, an unnamed pond | |
| Height above nearest drain | Not verified yet | |
| Club House, built | 0% | Review |
|---|---|---|
| Electricity, built | 0% | |
| Outdoor Sports facility, built | 0% | |
| Swimming Pool, built | 0% | |
| Power Backup, built | 0% | |
| Kitchen handover | Not verified yet | |
| Sewage plant | Not verified yet | |
| Power backup | Not verified yet | |

| Main structure | 100% · planned by 30 Jun 2025 | |
|---|---|---|
| Electrical and plumbing finishing | 32% · planned by 21 Jan 2026 | |
| Internal roads | Not verified yet | |
| Club house | Not started | |
| Completion | 83% | |
| Completion, accountant | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | 21 Jan 2026 | |
| RERA completion date | 20 Jan 2027 | |
| Completion date, agreement | 22 Jan 2026 | |
| Work began, as filed | 22 Jan 2020 | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Form 6 · Feb 2026 | Clear |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | Not verified yet | |
| Environmental clearance | SEIAA 75 CON 2019 · issued 23 Aug 2019 | |
| Architect, quarterly | Form 5 · Feb 2026 | |
Land · ₹3.87 Cr 6.4%Development · ₹56.78 Cr 93.6%
| Estimated cost | ₹60.65 Cr | |
|---|---|---|
| Cost incurred | Not verified yet | |
| Cost left | Not verified yet | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
Sold (95) 42.2%Unsold (130) 57.8%
| Sold, Q3 2025-26 | 95 / 225 · 130 available | |
|---|---|---|
| Unsold, Q3 2025-26 | 130 |
| Escrow bank | HDFC · MARATHAHALLI | |
|---|---|---|
| Designated account, collected | ₹9.41 Cr in Q3 2025-26 | |
| Designated account, withdrawn | ₹9.41 Cr in Q3 2025-26 (100% of that quarter's deposits) | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| Developer's project loan |
|---|
| Not verified yet |
| Records searched to | Not verified yet | |
|---|---|---|
| Building plan | Not verified yet | |
|---|---|---|
| Unregistered agreements, over 10% paid | Not verified yet | |
|---|---|---|
| Sale deed in favour of | Not verified yet | |
|---|---|---|
| Escrow bank | HDFC · MARATHAHALLI |
|---|

Map of 7 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Poetry Of Earth, price locked; Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 And 24, price locked; SOBHA Ayana, price locked; Sobha Dream Acres - Oasis Phase 27 Wing 55, 56, 57 And 58, price locked; SOBHA Neopolis, price locked; Reflections 66, price locked; Adarsh Parkland, price locked.
| Poetry Of Earth | 620 m | Locked | |
|---|---|---|---|
| Inspira Infinity | about 1 km | Locked | |
| Adarsh Park Heights Phase-2 | about 1.5 km | Locked | |
| Sobha Sentosa Phase 1 Wing 7 | about 1.5 km | Locked | |
| Sobha Sentosa Phase 2 Wing 5 And 6 | about 1.5 km | Locked | |
| Sobha Sentosa Phase 3 Wing 3 And 4 | about 1.5 km | Locked | |
| Sobha Sentosa Phase 4 Wing 1 And 2 | about 1.5 km | Locked | |
| Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 And 24 | 1.7 km | Locked | |
| SOBHA Ayana | 1.8 km | Locked | |
| Sobha Dream Acres - Tropical Greens Phase 21 Wing 21 And 22 | about 2 km | Locked | |
| Sobha Dream Acres - Oasis Phase 27 Wing 55, 56, 57 And 58 | 1.9 km | Locked | |
| Jeevan's Allure | about 3 km | Locked |
| Desire Tree This project | This project is the point the others are measured from | 20 Jan 2027 | 42% (95 of 225) | Not verified yet |
|---|---|---|---|---|
| Poetry Of Earth | 620 m | 31 Dec 2028 | 23% (65 of 282) | Locked |
| Inspira Infinity | about 1 km | 31 Jan 2029 | 95% (100 of 105) | Locked |
| Adarsh Park Heights Phase-2 | about 1.5 km | 31 May 2027 | 95% (471 of 494) | Locked |
| Sobha Sentosa Phase 1 Wing 7 | about 1.5 km | 30 Jun 2026 | 100% (71 of 71) | Locked |
| Sobha Sentosa Phase 2 Wing 5 And 6 | about 1.5 km | 31 Dec 2026 | 99% (140 of 142) | Locked |
| Sobha Sentosa Phase 3 Wing 3 And 4 | about 1.5 km | 30 Jun 2027 | 99% (176 of 178) | Locked |
| Rent, 4BHK, 3 km | ₹1,20,000 /mo · 6 listings | |
|---|---|---|
| Rent, 3BHK, 3 km | ₹60,000 /mo · 54 listings | |
| Rent, 2BHK, 3 km | ₹40,000 /mo · 124 listings | |
| Rent, 1BHK, 3 km | ₹19,000 /mo · 86 listings | |
| Rent per sq ft, 3 km | ₹36.9 /mo, as listed · 137 listings with a size | |
| Gross yield | Not verified yet | |
| Gross yield, per sq ft | Not verified yet | |
| Bengaluru median yield | Not verified yet | |
| Projects within 4 km, counted | 88 (39 with an approximate location) | |
|---|---|---|
| Flats in them | 30,007 | |
| Booked | 18,219 of 30,007 (61%) | |
| Unsold | 11,788 | |
| Booked a month, pooled | 503 flats | |
| Months to sell, pooled | 23 months |
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 30.5 m
Across Bengaluru East, the water table sat 27.3 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 30.5 m, and it recovered 1.9 m over the year.
| Groundwater | Bengaluru East taluk average, July 2023: 27.3 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 27.3 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Local authority | |
| Nearest city water main | 1.8 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | 100 m to the south, tertiary drain | |
| Ground level | Not verified yet | |
| Metro, operational | 4.2 km, Nallur Halli | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 28.9 |
| MG Road (CBD) | 15.4 |
| Manyata Tech Park | 17.3 |
| ITPL, Whitefield | 5.0 |
| Ecospace, Bellandur ORR | 6.6 |
| Electronic City Ph 1 | 13.2 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | 2.2 km to the west, named Bellandur Amani 90MLD Sewage Treatment Plant on OpenStreetMap | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 1.1 km to the north-east |