Overview
Overview
Overview

Title & ownership
Approvals
Disputes & cases
Contract & costs
Valuation
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
What we read
Source: K-RERA project page and the documents filed there, as read by us. 61 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | 1 | – | 3 | Red flag |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Locked |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | 2 | Clear |
| Loan & collateral | – | 1 | – | Review |
Part of the full report. Unlock all 4 sections
| Agm BuildersApplied for completion 16/07/2026 | AGM BUILDERS | Plot | ~1,200–1,500 sqft (estimate: filed carpet plus 25%) | Dec 2029 |
| Aikam Golf Estates Phase IRegistered · no quarterly update yet | BCD EMPRASA LIMITED LIABILITY PARTNERSHIP | Plot | ~1,160–1,810 sqft (estimate: filed carpet plus 25%) | Dec 2026 |
| Asn Sai EnclaveLapsed · completion date passed | ANKURAA SAI NITYA ESTATES | Plot | – | Mar 2021 |
| Back To LifeApplied for completion 05/04/2019 | Azven Realty Ventures Private Limited | Plot | – | Dec 2019 |
| Emprasa Startup City - ResidentialLapsed · completion date passed | HOSKOTE NEO HOMES LIMITED | Apartment | 409 sqft carpet (as filed) | Dec 2023 |
| Grovin Green CityApplied for completion 07/05/2024 | M/S GROVIN DEVELOPERS | Plot | – | Feb 2022 |
| House Of SapiensRegistered · no quarterly update yet | MA SARADA CONSTRUCTIONS | Apartment | 738–2,147 sqft carpet (as filed) | Jan 2031 |
| Sj Green WoodsLapsed · completion date passed | SJ Developers | Plot | – | Dec 2021 |
8 of 9 other projects in Hoskote, A to Z. Status is taken from each project's own filing.
All 12 projects in Hoskote → · Sowparnika Projects's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Sowparnika Indradhanush Phase I in the interactive atlas
₹99 for this report opens Valuation, Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Valid as of this reportValidity ended
| Building plan (Local Planning Authority) | Sanctioned 11 Mar 2022 · No. HPA/CC/137/2021-22 | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire NOC | KSFES/NOC/305/2021 · issued 3 Jan 2022 | Clear |
| Environmental clearance | SEIAA 101 CON 2021 · EC identification no. EC21B038KA132702 · issued 28 Dec 2021 | Clear |
| Airport height NOC | valid until 1 Sep 2029 | Clear |
| Pollution board (CFE) | Filed with the registration | |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 2 | |
| RERA completion date | 31 May 2027 |
| Land conversion | Converted 13 Dec 2018 · Deputy Commissioner, Bangalore Rural | |
|---|---|---|
| Survey numbers | 150300401201200581 |
₹99 for this report opens Valuation, Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | Not verified yet | |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | about 12.5 km, SAI BABA ASHRAM KADUGODI | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed water body | |
| Height above nearest drain | Not verified yet | |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Amenities declared | Electricity · CCTV Surveillance · Power Backup · Water and Sanitation | |
|---|---|---|
| Electricity, built | 60% | |
| Power Backup, built | 0% | |
| Kitchen handover | Not verified yet | |
| Covered parking per unit | 0.58 (332 covered spaces for 570 units) | |
| Sewage plant | Not verified yet | |
| Power backup | Declared by the promoter | |
Ten-year July mean for this taluk: 62 m
Across Hosakote, the water table sat 22.6 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 62 m, and it recovered 4.9 m over the year.
| Groundwater | Hosakote taluk average, July 2023: 22.6 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 22.6 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell | |
| Nearest city water main | Not verified yet | |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
As the promoter reported it

| Main structure | 100% · planned by 31 Dec 2024 | |
|---|---|---|
| Electrical and plumbing finishing | 80% · planned by 31 Mar 2027 | |
| Internal roads | Not verified yet | |
| Club house | Not verified yet | |
| Completion | 100% | |
| Completion, accountant | 98.7% of the estimated cost spent | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | 30 May 2027 | |
| RERA completion date | 31 May 2027 | |
| Work began, as filed | 1 Jun 2022 | |
| Structure | Not verified yet | |
|---|---|---|
| Foundation | Not verified yet | |
| Wall material | Not verified yet | |
| Wall thickness | Not verified yet | |
| Concrete / steel grade | Not verified yet | |
| Building heights, fire NOC | 40 m filed | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | UPVC windows | |
|---|---|---|
| Flooring | Vitrified tiles | |
| Toilet tiles, spec vs brochure | Not verified yet | |
| Wiring | Concealed copper wiring | |
| Sanctioned load per flat | Not verified yet | |
| Power backup | 100% power backup for common areas | |
| Sewage plant | Not verified yet | |
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | KSFES/NOC/305/2021 · issued 3 Jan 2022 | |
| Environmental clearance | SEIAA 101 CON 2021 · EC identification no. EC21B038KA132702 · issued 28 Dec 2021 | |
| Architect, quarterly | Form 5 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | |
| Architect's certificate, registration | Dated 25 Apr 2022 · site inspected 24 Apr 2022 | |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹6.98 Cr 4.1%Development · ₹163.82 Cr 95.9%
| Estimated cost | ₹170.80 Cr | |
|---|---|---|
| Estimated cost, architect's and engineer's certificates | ₹84.34 Cr | |
| Estimated cost, Form 4 Q1 2026-27 | ₹217.75 Cr | |
| Cost incurred | ₹214.89 Cr (98.7% of the estimate) | |
| Cost left | ₹2.86 Cr | |
| Collected from buyers | ₹194.14 Cr | |
| Receivable, sold flats | ₹36.87 Cr | |
| Land cost revision | Not verified yet | |
Sold (567) 99.5%Unsold (3) 0.5%
| Sold, Q3 2025-26 | 566 / 570 · 4 available | |
|---|---|---|
| Sold, Q4 2025-26 | 567 / 570 · 3 available | |
| Sold, Q1 2026-27 | 567 / 570 · 3 available | |
| Sold, Q2 2026-27 | 567 / 570 · 3 available | |
| Unsold, Q2 2026-27 | 3 | |
| Sold in Q4 2025-26 | 1 | |
| Sold in Q1 2026-27 | 0 | |
| Sold in Q2 2026-27 | 0 |
| Escrow bank | HDFC · OLD AIRPORT ROAD | |
|---|---|---|
| Designated account, collected | ₹2.19 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹2.19 Cr in Q2 2026-27 (100% of that quarter's deposits) | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 2 | |
| Developer's project loan | Catalyst Trusteeship Ltd · ₹6.60 Cr disbursed | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan | Sanctioned 11 Mar 2022 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | HDFC · OLD AIRPORT ROAD | |

Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | None within 3 km | |
| Ground level | Not verified yet | |
| Metro, operational | about 13 km, Whitefield | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 15.5 |
| MG Road (CBD) | 26.5 |
| Manyata Tech Park | 21.5 |
| ITPL, Whitefield | 15 |
| Ecospace, Bellandur ORR | 24 |
| Electronic City Ph 1 | 32.5 |
| Sewage treatment plant |
|---|
| None within 3 km |
| Quarry | None within 3 km |
|---|
| Crematorium | None within 3 km |
|---|
| Prison | None within 3 km |
|---|
| Electrical substation | about 2 km to the north-east |
|---|