Overview
Overview
Overview
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 1 | – | |
Other sites that list or cover this project. DOSL does not vouch for them, and they can be older than the filing above.
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Aishwarayam TranquilLapsed · completion date passed | MS AISHWARYAM CONCEPT HOMES | Apartment | 807 sqft carpet (as filed) | Mar 2023 |
| Akruthi Spring WoodsLapsed · completion date passed | DAI DORON INDIA PROPERTIES PVT. LTD. | Plot | – | Apr 2019 |
| Akshaya MeadowsLapsed · completion date passed | M/s Akshaya Meadows | Plot | ~1,080–1,800 sqft (estimate: filed carpet plus 25%) | Apr 2026 |
| AmaryllisLapsed · completion date passed | RAKI DEVELOPERS LLP | Apartment | 780–1,047 sqft carpet (as filed) | Jul 2026 |
| Ambiant - Maangalya AshirvadActive · 22% built | AMBIANT HOUSING & CONSTRUCTION PVT LTD. | Apartment | 896–1,171 sqft carpet (as filed) | Apr 2028 |
| Aqua VistaLapsed · completion date passed | POPPY REALTORS PRIVATE LIMITED | Apartment | 323–5,371 sqft carpet (as filed) | Dec 2024 |
| Artha Satori Platinum | Artha Group | Villa | 4,780 sqft | – |
| Arvind SkycrestActive · 1% built | Arvind SmartSpaces | Apartment | 1,131–1,944 sqft | Mar 2031 |
8 of 190 other projects in Bannerghatta Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Artha Zen in the interactive atlas
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Aqua Vista | about 2 km | Locked | |
|---|---|---|---|
| Azur Tower D | 2.2 km | Locked | |
| Azur Phase 2 | about 2.5 km | Locked | |
| Lodha Azur | 2.7 km | Locked |
| Artha Zen This project | This project is the point the others are measured from | Not on the filing | Not filed | Not verified yet |
|---|---|---|---|---|
| Aqua Vista | about 2 km | 31 Dec 2024 | 96% (173 of 181) | Locked |
| Azur Tower D | 2.2 km | 30 Apr 2030 | 93% (110 of 118) | Locked |
| Azur Phase 2 | about 2.5 km |
Map of the ground within about 450 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | BMICAPA planning area (NICE corridor) | |
|---|---|---|
| Nearest high-tension line | A 220 kV line runs along the site's edge, its corridor taking about 1% (about 150 m²) | Review |
| Nearest government-flagged flood location | 1.7 km, BDA LAYOUT | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | 60 m to the west, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 240 m to the north-west, Kammanahalli Lake | |
| Height above nearest drain | Not verified yet | |
Map of storm drains, lakes and government-flagged flood locations within about 450 m of the site.
Ten-year July mean for this taluk: 23.2 m
Across Bengaluru South, the water table sat 16.9 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 23.2 m, and it fell 4.2 m over the year.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 16.9 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Not verified yet | |
| Nearest city water main | 780 m | |
Map of 3 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Azur Tower D, price locked; Lodha Azur, price locked; Assetz Canvas & Cove 2.0 - Block A, price locked.
| Iris Courtyard | about 3 km | Locked |
|---|
| Assetz Canvas & Cove 2.0 - Block A | 3.5 km | Locked |
|---|
| Assetz Canvas & Cove - Phase 1 Wing A & B | about 3.5 km | Locked |
|---|
| Platinum Landmark | about 4 km | Locked |
|---|
| K&T's Sai Sannidhi | 4.2 km | Locked |
|---|
| Mahindra NewHaven | 4.4 km | Locked |
|---|
| Dhiraan Lotus | about 4.5 km | Locked |
|---|
| Mahindra Zen | 4.7 km | Locked |
|---|
| 31 Dec 2030 |
| 86% (185 of 214) |
| Locked |
| Lodha Azur | 2.7 km | 30 Oct 2029 | 97% (236 of 244) | Locked |
|---|
| Iris Courtyard | about 3 km | 30 Jun 2026 | 30% (12 of 40) | Locked |
|---|
| Assetz Canvas & Cove 2.0 - Block A | 3.5 km | 30 Apr 2029 | 98% (238 of 244) | Locked |
|---|
| Rent, 3BHK, 3 km | ₹47,000 /mo · 30 listings | |
|---|---|---|
| Rent, 2BHK, 3 km | ₹30,000 /mo · 39 listings | |
| Rent, 1BHK, 3 km | ₹11,750 /mo · 16 listings | |
| Rent per sq ft, 3 km | ₹26.0 /mo, as listed · 48 listings with a size | |
| Gross yield | Not verified yet | |
| Gross yield, per sq ft | Not verified yet | |
| Bengaluru median yield | Not verified yet | |
| Projects within 4 km, counted | 40 (21 with an approximate location) | |
|---|---|---|
| Flats in them | 11,755 | |
| Booked | 8,627 of 11,755 (73%) | |
| Unsold | 3,128 | |
| Booked a month, pooled | 240 flats | |
| Months to sell, pooled | 13 months |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | 60 m to the west, tertiary drain | |
| Ground level | Not verified yet | |
| Metro, operational | Not verified yet | |
| Metro, under construction | 2.5 km, Kalena Agrahara | |
| Kempegowda Airport | 39.9 |
| MG Road (CBD) | 13.7 |
| Manyata Tech Park | 21.4 |
| ITPL, Whitefield | 20.4 |
| Ecospace, Bellandur ORR | 11.3 |
| Electronic City Ph 1 | 7.8 |
| Landfill or waste transfer station | 2.5 km to the west | |
|---|---|---|
| Sewage treatment plant | 890 m to the east, named STP on OpenStreetMap | |
| Quarry | 1.0 km to the south-east | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 750 m to the east, named Power Transformers - PU on OpenStreetMap |